Get building plans approved by Machakos County

County Government of Machakos · sources read 3 Oct 2026

Apply to the county's Director of Physical Planning with three copies of your plans and your title deed. In urban areas you pay a KSh 2,000 application fee plus KSh 40 per m² for a house (KSh 60 for commercial), and the county should review it within 30 days.

Fee
KSh 2,000Application fee: urbanKSh 1,000Application fee: peri-urbanKSh 500Application fee: ruralKSh 40Architectural approval: residential, urban, per m²KSh 30Architectural approval: residential, rural, per m²KSh 60Architectural approval: commercial, urban, per m²KSh 5,000Building inspection fee: urbanKSh 2,000Public health fee: bungalow, urbanKSh 50Certificate of occupation: residential, urban, per m²KSh 1,000Renewal of a building plan (application)
How long
The Director should review your application within 30 days.
Where
In person at the Department of Lands, Housing and Urban Development, along Mwatu wa Ngoma Road, opposite the County Commissioner's office, Machakos. Call 0800 600 016 or email lands@machakos.go.ke.
Go to the official site

What you need

  • Certificate of title (title deed) for the plot
  • Floor plans, elevations, sections and a block plan of the building and site
  • Three copies of the application (four for factories)
  • Engineer's certificate for steel, reinforced concrete or timber structures
  • NEMA-approved EIA report, if your project needs one

Steps

  1. Get your plans drawn: every floor, the elevations, sections and a block plan. Steel or concrete structures need an engineer's certificate.
  2. Apply to the county's Director of Physical Planning on the prescribed form, with three copies and your title deed.
  3. Pay the application fee (KSh 2,000 urban, 1,000 peri-urban, 500 rural) and the approval fee for your floor area.
  4. Wait for the review. The Director should consider it within 30 days.
  5. Once approved, give the county planner at least 4 days' written notice before you start building.

Watch out

  • Start building within 12 months of approval, or the approval lapses.
  • A share certificate won't do. The county only accepts a title deed.
  • If your plans are turned down, the county must tell you why within 30 days.

Who can apply

  • Anyone carrying out development in Machakos County needs development permission first.
  • You need a title deed. A share certificate is not accepted as proof of ownership.
Official sources (2)
  1. The Machakos County Finance Act, 2025 machakos.go.ke · read 3 Oct 2026
  2. Lands, Urban Development, Housing & Roads (County Government of Machakos) machakos.go.ke · read 3 Oct 2026

Was this helpful?

Share on WhatsApp · Report a mistake

Don't include your ID number or KRA PIN. We remove them if you do.