How long building approval lasts, and building differently from approved plans

Physical and Land Use Planning Act · sources read 2 Oct 2026

County building approval (development permission) lapses if you do not start building within 3 years, though the county can extend it by 1 year. Building works that do not match the approved plans are an offence, so apply to the county again for any material change.

Deadline
3 years from approval to start building, or the permission lapses.
Deadline
5 years to complete the building works before the county may add conditions or a fine.
Deadline
14 days from being served with an enforcement notice to appeal.
Where
Your county government's physical planning office; appeals to the County Physical and Land Use Planning Liaison Committee.
Read the law

Steps

  1. If you cannot start within 3 years, apply to the county planning office to extend the permission by 1 year.
  2. If you want to change the design materially, apply to the county for development permission for the variation before building it.
  3. If you get an enforcement notice, you can appeal to the County Liaison Committee within 14 days of being served.

Watch out

  • Building works inconsistent with the approved plans, or ignoring approval conditions, is an offence with a fine of at least KSh 1 million or at least 5 years in jail.
  • The county can serve an enforcement notice requiring you to alter or demolish the works within a set time.

Who this covers

  • Anyone who has been granted development permission by a county.
  • Anyone can inspect the county's register of development permissions, for example to check a neighbour's approval.
Official sources (1)
  1. Physical and Land Use Planning Act (No. 13 of 2019, Cap. 303) new.kenyalaw.org · read 2 Oct 2026