Apply for net metering to export rooftop solar power to the grid

Kenya Power and Lighting Company · sources read 3 Oct 2026

Send the Form 001 net-metering application to your electricity distributor with your documents; systems over 10 kW also need an engineer's feasibility study. The distributor must decide within 60 days, and you get credit for 50% of each unit you export.

Fee
We couldn't confirm a fee from the official page. Check it there before you pay.
How long
Decision within 60 days of applying
Where
In writing to your electricity distribution licensee (your power supplier), using Form 001 from the Energy (Net-Metering) Regulations, 2024
Go to KPLC

What you need

  • Completed Form 001 (from the Net-Metering Regulations), with your KRA PIN and electricity account number
  • Certified copy of your ID document
  • Lease agreement or title deed for the land where the system is installed
  • KRA PIN certificate
  • Feasibility study report by a registered engineer (required for systems over 10 kW)
  • Companies: certificate of incorporation, CR12 (within 12 months), directors' IDs, PIN, VAT and tax compliance certificates

Steps

  1. Fill in Form 001 and send it to your electricity distributor with certified copies of your documents.
  2. Wait for the decision. The distributor must reply within 60 days, giving conditions if approved or reasons if rejected.
  3. If approved, sign the net-metering agreement and pay the non-refundable deposit and fees approved by EPRA.
  4. Install and commission the smart two-way meter within 6 months, using an authorised installer. Give the distributor 14 days' written notice to witness testing.
  5. File a copy of the signed agreement with EPRA within 30 days of signing.

Watch out

  • You are credited only 50% of each unit you export, not the full unit.
  • Unused credits roll over month to month but are lost at the end of the distributor's financial year.
  • If the meter isn't installed and commissioned within 6 months of signing, the application is cancelled.

Who can apply

  • Electricity customers generating from a renewable source (like solar) of less than 1 MW.
  • Homes: up to 4 kW on single-phase supply or 10 kW on three-phase.
Official sources (1)
  1. The Energy (Net-Metering) Regulations, 2024 (Legal Notice No. 104 of 2024) epra.go.ke · read 3 Oct 2026